9 hours to transform the railway station, these Chinese speed is subverting your imagination!#1

in #cn7 years ago

How long does it take to transform a railway station?

You can not think of it

9 hours! Just nine hours

This miracle is called China's speed!

0.gif

Railway station major transformation

More than 1,500 people working in the same field for 9 hours

January 19 evening

With the scene commander orders

More than 1,500 people quickly put into construction

South (peace) three (Ming) Long (rock) railway

Fujian Longyan station transformation began

The construction is a very rare railway I-class construction

Up to dozens of construction machines

Time is more stressful

Starting from 18:30 the same day

Only about 9 hours

It is necessary to complete the turnout demolition shop, draw mouth dial

Signal Dressup and all other homework

0-2.gif

The scene is like a movie blockbuster

More than 1,500 railway people do not sleep endlessly

Overnight

Completed the Longyan Railway Station between the old and new station

Line transition large construction

0-3.gif

After running to determine the safety and stability of the equipment

Longyan Station's new platform officially put into use

And with the new look to meet the 2018 Spring Festival passenger flow

640-2.jpeg

This construction

It also creates conditions for the opening of the Nanping-Longyan railway under construction at the end of the year

Between the two places when the train running time

Will be shortened from 7 hours to 1.5 hours